PULSE REPORT WEEK 11

 

What was happening in last week?

1.We just found another way which is it causes more efficient on producing (certain design)

2.Our Second Pre-Order was delayed last time because of some problems, but this week, it is processed again

The differences between plan and real
(THE FACTORS)

1.We started producing in March, not in April (as planned).

2.Our loan capital was planned Rp 1.760.000, but what is real, we only got Rp 1.500.000. (not as factor)

3.We did not expect of other expenses (unexpected expenses), such as Vendor Services; Fail on Producing; Launching Cost; and other.

4.Our product price.

(In this powerpoint we created line chart of our finance, the file is attached on dropbox by clicking on this link below)

 

(created by Betti, 41170002)

https://www.dropbox.com/s/2q0k13y6v1eig4v/pulse%20report%2011.pptx?dl=0